• OPERATION NAME: Massey
  • SUBMIT DATE: 11-19-2018
  • NOAP ID: 2018-711-14394 (c)
  • LANDOWNER STATUS: The Landowner is not a Small Forestland Owner.
  • Apply for a permit to use fire or power-driven machinery (PDM) (ORS 477.625)
  • Notify for an operation (excludes applying pesticides by helicopter) (ORS 527.670)
  • Before you use fire, contact the local office of the Oregon Department of Forestry or Forest Protective Association to see if additional burn permit and/or Smoke Management Program regulations apply.

NOAP CONTINUATIONS

  • Issued on: 01-24-2019
    Expires on: 12-31-2019
    Continuation issued by Steve Wetmore

Oregon Department of Forestry Contact Information

ODF OFFICE: MEDFORD
ODF DISTRICT:
Southwest Oregon
ADDRESS:
5286 Table Rock Rd
Central Point, Oregon, 97502
PHONE:
(541) 664-3328
ODF FORESTER
NAME:
Nick Haile

Notifier

JUSTIN MOORE
COMPANY:
Lomakatsi Restoration Project
ADDRESS:
645 Washington St
Ashland , Oregon, 97520
PHONE:
(541) 488-0208
EMAIL:
Not Available

Notifier Comment

No Notifier comments have been made on this NOAP.

Landowner(s)

Landowner Responsibility
JENNIFER MASSEY
ADDRESS:
200 Beacon Hill Ln.
Ashland, Oregon, 97520
PHONE:
(541) 488-1912
Landowner Responsibility

The Landowner is responsible for reforestation. Early consultation with the ODF Forester is advised.

On-site inspections may be conducted by Oregon Department of Forestry employees to ensure compliance with all laws and rules governing fire protection and forest practices on private land.

For activities or operations changing the land to a non-forest use, the applicant is advised to contact the appropriate local government regarding land use regulations which may apply to the future use or development of this site.)

Fire Emergency Contact

NAME:
Jonathan Paul
PHONE:
(541) 646-1433

Units / Activities / Operators

3.4 ACRES
  • Fuels Reduction

    METHOD(S):
    Manual
    OPERATOR:
    Lomakatsi Restoration Project
    COMPANY:
    Lomakatsi Restoration Project
  • Use of Fire

    METHOD(S):
    Burn Piles
    OPERATOR:
    Lomakatsi Restoration Project
    COMPANY:
    Lomakatsi Restoration Project

This Unit falls within the following Regulated Use Areas: SW-2

Site Conditions

ADDITIONAL REGULATIONS MAY APPLY
  • Slope of steepest 1/3 area: 50 %.

Uploaded Documents

You must be signed in as a registered user with FERNS to see documents associated with this NOAP.

Formal Comments

COMMENTS
  • Steve Wetmore
    1/24/2019 1:05:28 PM
    Continued until 12/31/2019
  • Nick Haile
    11/26/2018 3:59:03 PM
    Resource review is complete. All streams are Small Type N streams. No other FPA protected resources at this time.