- OPERATION NAME: Rock Pits
- SUBMIT DATE: 01-05-2016
- NOAP ID: 2016-552-00383 (c)
- LANDOWNER STATUS: The Landowner is not a Small Forestland Owner.
- Apply for a permit to use fire or power-driven machinery (PDM) (ORS 477.625)
- Notify for an operation (excludes applying pesticides by helicopter) (ORS 527.670)
NOAP CONTINUATIONS
-
Issued on: 12-22-2016Expires on: 12-31-2017Continuation issued by Jennifer Erdmann
Oregon Department of Forestry Contact Information
ODF OFFICE: DALLAS
Dallas, Oregon, 97338
ODF FORESTER
Notifier
TOM LORD
- COMPANY:
- Weyerhaeuser
- ADDRESS:
- 34904 Brester Rd
Lebanon, Oregon, 97355 - PHONE:
- (503) 508-6479
- EMAIL:
- Not Available
Landowner(s)
WYTHI DALLAS
- COMPANY:
- Weyerhaeuser Timber Holdings, Inc.
- ADDRESS:
- 900 SE Monmouth Cutoff Road
Dallas, Oregon, 97338 - PHONE:
- (503) 623-7142
The Landowner is responsible for reforestation. Early consultation with the ODF Forester is advised.
On-site inspections may be conducted by Oregon Department of Forestry employees to ensure compliance with all laws and rules governing fire protection and forest practices on private land.
For activities or operations changing the land to a non-forest use, the applicant is advised to contact the appropriate local government regarding land use regulations which may apply to the future use or development of this site.)
Fire Emergency Contact
- NAME:
- Weyco Fire Plan
- PHONE:
- (503) 623-7142
Legal Notice
WRITTEN PLANS
A Written Plan (in addition to this NOAP) is required before operation activities can begin near the protected resources listed with the Unit information or Site Conditions below or otherwise described to you by the ODF Forester (OAR 629-605-0170(2), (3), and (5)). The Written Plan must describe in detail how the resource(s) will be protected during the operation. There is a waiting period for Written Plans that is separate from the notification waiting period. Contact your ODF Forester for more information.
Units / Activities / Operators
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
A Statutory Written Plan is required for the resources detected in or near this Unit if activities occur within:
- Unknown: - Type F Stream
- None detected.
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
A Statutory Written Plan is required for the resources detected in or near this Unit if activities occur within:
- Unknown: - Type F Stream
- None detected.
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
A Statutory Written Plan is required for the resources detected in or near this Unit if activities occur within:
- Unknown: - Type F Stream
- None detected.
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
-
Rock Pit Development/Management
- METHOD(S):
- Mechanical
- OPERATOR:
- WYNR Dallas
- COMPANY:
- Weyerhaeuser NR
Site Conditions
- Stream within 100 feet of area.
- Slope of steepest 1/3 area: 25 %.
Uploaded Documents
You must be signed in as a registered user with FERNS to see documents associated with this NOAP.
Formal Comments
-
Jennifer Erdmann
12/22/2016 9:12:59 AM
NOAP continued per request of landowner for 2017.
-
Dave Thompson
1/7/2016 4:46:22 PM
A Statutory Written Plan is required for any of the Mill Creek rock pits in which operational activity will directly affect the physical components of the RMA of Mill Creek or any of the associated Type F tributaries.