• OPERATION NAME: Number 1
  • SUBMIT DATE: 11-18-2015
  • NOAP ID: 2015-711-14487 (c)
  • LANDOWNER STATUS: The Landowner is not a Small Forestland Owner.
  • Apply for a permit to use fire or power-driven machinery (PDM) (ORS 477.625)
  • Notify for an operation (excludes applying pesticides by helicopter) (ORS 527.670)
  • Notify the Departments of Forestry and Revenue of my intent to harvest timber (ORS 321.550)
  • Before you use fire, contact the local office of the Oregon Department of Forestry or Forest Protective Association to see if additional burn permit and/or Smoke Management Program regulations apply.

NOAP CONTINUATIONS

  • Issued on: 01-05-2016
    Expires on: 12-31-2016
    Continuation issued by Tyson Schultz

Oregon Department of Forestry Contact Information

ODF OFFICE: MEDFORD
ODF DISTRICT:
Southwest Oregon
ADDRESS:
5286 Table Rock Rd
Central Point, Oregon, 97502
PHONE:
(541) 664-3328
ODF FORESTER
NAME:
Bob Marcu

Notifier

JACOB GROVES
COMPANY:
Chinook Forest Management
ADDRESS:
1867 Williams Hwy, Suite 109C
Grants Pass, Oregon, 97527
PHONE:
(541) 295-5851
EMAIL:
Not Available

Notifier Comment

No Notifier comments have been made on this NOAP.

Landowner(s)

Landowner Responsibility
JOHN MURPHY
COMPANY:
Murphy Timber Investments
ADDRESS:
2350 Prairie Road
Eugene, Oregon, 97402
PHONE:
(541) 461-1200
Landowner Responsibility

The Landowner is responsible for reforestation. Early consultation with the ODF Forester is advised.

On-site inspections may be conducted by Oregon Department of Forestry employees to ensure compliance with all laws and rules governing fire protection and forest practices on private land.

For activities or operations changing the land to a non-forest use, the applicant is advised to contact the appropriate local government regarding land use regulations which may apply to the future use or development of this site.)

Timber Owner

Timber Owner Responsibility
JOHN MURPHY
COMPANY:
Murphy Timber Investments
ADDRESS:
2350 Prairie Road
Eugene, Oregon, 97402
PHONE:
(541) 461-1200
Timber Owner Responsibility

If timber harvesting is part of the proposed operation, the party shown below, owning the timber at the point it is first measured, is responsible for payment of Oregon timber taxes.

Fire Emergency Contact

NAME:
Jacob Groves
PHONE:
(541) 736-6646

Units / Activities / Operators

111.6 ACRES
  • Clearcut/Overstory Removal

    METHOD(S):
    Cable, Ground
    OPERATOR:
    Travis Myers
    COMPANY:
    GM Land & Forest LLC
  • Treatment of Slash

    METHOD(S):
    Burning - piles
    OPERATOR:
    John Murphy
    COMPANY:
    Murphy Timber Investments

Site Conditions

ADDITIONAL REGULATIONS MAY APPLY
  • Slope of steepest 1/3 area: 30 %.

Uploaded Documents

You must be signed in as a registered user with FERNS to see documents associated with this NOAP.

Formal Comments

COMMENTS
  • Allison Blair
    10/26/2016 12:49:26 PM
    added activity of slash burn 10/26/2016 AB
  • Tyson Schultz
    1/5/2016 9:23:07 AM
    Continued for 2016.
  • Bob Marcu
    11/23/2015 5:44:09 PM
    Stream Resources = Tributary to Dodes Creek (S-N); No significant RMA issues; Wildlife Resources = No significant protected wildlife issues; RLM