• OPERATION NAME: Dirt Bag Timber Sale 2022
  • SUBMIT DATE: 04-26-2022
  • NOAP ID: 2022-781-05699 (c)
  • LANDOWNER STATUS: The Landowner is not a Small Forestland Owner.
  • Apply for a permit to use fire or power-driven machinery (PDM) (ORS 477.625)
  • Notify for an operation (excludes applying pesticides by helicopter) (ORS 527.670)
  • Notify the Departments of Forestry and Revenue of my intent to harvest timber (ORS 321.550)
  • Before you use fire, contact the local office of the Oregon Department of Forestry or Forest Protective Association to see if additional burn permit and/or Smoke Management Program regulations apply.

NOAP CONTINUATIONS

  • Issued on: 01-30-2023
    Expires on: 12-31-2023
    Continuation issued by Fiona Christensen

Oregon Department of Forestry Contact Information

ODF OFFICE: FLORENCE
ODF DISTRICT:
Western Lane
ADDRESS:
2660 Kingwood St
Florence, Oregon, 97439
PHONE:
(541) 972-0211
ODF FORESTER
NAME:
Tim Moss

Notifier

QUINCY COONS
COMPANY:
Mason Bruce & Girard
ADDRESS:
40 Irving Rd
Eugene, Oregon, 97404
PHONE:
(541) 556-4383
EMAIL:
Not Available

Notifier Comment

No Notifier comments have been made on this NOAP.

Landowner(s)

Landowner Responsibility
. .
COMPANY:
New Growth LLC, c/o FIA, c/o Mason Bruce & Girard
ADDRESS:
40 Irving Rd
Eugene, Oregon, 97404
PHONE:
(541) 973-5232
Landowner Responsibility

The Landowner is responsible for reforestation. Early consultation with the ODF Forester is advised.

On-site inspections may be conducted by Oregon Department of Forestry employees to ensure compliance with all laws and rules governing fire protection and forest practices on private land.

For activities or operations changing the land to a non-forest use, the applicant is advised to contact the appropriate local government regarding land use regulations which may apply to the future use or development of this site.)

Timber Owner

Timber Owner Responsibility
. .
COMPANY:
New Growth LLC, c/o FIA, c/o Mason Bruce & Girard
ADDRESS:
40 Irving Rd
Eugene, Oregon, 97404
PHONE:
(541) 973-5232
Timber Owner Responsibility

If timber harvesting is part of the proposed operation, the party shown below, owning the timber at the point it is first measured, is responsible for payment of Oregon timber taxes.

Fire Emergency Contact

NAME:
Quincy Coons
PHONE:
(541) 556-4348

Units / Activities / Operators

  • Clearcut/Overstory Removal

    METHOD(S):
    Cable, Ground
    OPERATOR:
    Quincy Coons
    COMPANY:
    Mason Bruce & Girard
  • Treatment of Slash

    METHOD(S):
    Burning - piles
    OPERATOR:
    Tim Sweet
    COMPANY:
    Rye Tree Service Inc.

This Unit falls within the following Regulated Use Areas: WT-1

A Statutory Written Plan is required for the resources detected in or near this Unit if activities occur within:

100 Feet of
  • Unknown: - Type F Stream
  • Wetlands: Freshwater Emergent Wetland, Freshwater Forested/Shrub Wetland
300 Feet of
  • NS Owl
  • Clearcut/Overstory Removal

    METHOD(S):
    Cable, Ground
    OPERATOR:
    Quincy Coons
    COMPANY:
    Mason Bruce & Girard
  • Treatment of Slash

    METHOD(S):
    Burning - piles
    OPERATOR:
    Tim Sweet
    COMPANY:
    Rye Tree Service Inc.

This Unit falls within the following Regulated Use Areas: WT-1

A Statutory Written Plan is required for the resources detected in or near this Unit if activities occur within:

100 Feet of
  • Unknown: - Type F Stream
  • Wetlands: Freshwater Emergent Wetland, Freshwater Forested/Shrub Wetland
300 Feet of
  • NS Owl

Site Conditions

RESOURCES THAT MAY REQUIRE A WRITTEN PLAN
  • Stream within 100 feet of area.
ADDITIONAL REGULATIONS MAY APPLY
  • Slope of steepest 1/3 area: 85 %.

Uploaded Documents

You must be signed in as a registered user with FERNS to see documents associated with this NOAP.

Formal Comments

COMMENTS
  • Tim Moss
    1/31/2023 12:45:16 PM
    If slash piles will be burned within 100 feet of a large fish stream, a written plan specifically stating how these waters of the state will be protected during burning activities will be required.
  • Tim Moss
    1/31/2023 12:45:04 PM
    This notification alone does not permit you to burn. In addition to your notification to burn slash, once you have your slash piled, you must also submit a smoke management registration at the Western Lane office in Veneta and then get verbal permission from the smoke management team. Please keep in mind that there is a 7 day waiting period after the day smoke registrations are submitted before you can request a burn day.
  • Fiona Christensen
    1/30/2023 11:39:43 AM
    Per emailed request by Quincy Coons on 12/15/2022, this notification is continued through 2023.
  • Tim Moss
    6/13/2022 2:49:29 PM
    Fully implementing this written plan will likely achieve the resource protection standards of Forest Practices Act. This operation will be evaluated on the basis of how well required resource protection is achieved.
  • Tim Moss
    6/13/2022 2:49:17 PM
    Resource Review Complete.
  • David Kjosness
    4/26/2022 2:37:46 PM
    To view electronic subscribers to the area of this operation, at the top of this page, click on "I WANT TO", then click on "VIEW SUBSCRIBERS".