• OPERATION NAME: Barnhart Wills 2022 Clearcut
  • SUBMIT DATE: 03-09-2022
  • NOAP ID: 2022-552-03625
  • LANDOWNER STATUS: The Landowner is not a Small Forestland Owner.
  • Apply for a permit to use fire or power-driven machinery (PDM) (ORS 477.625)
  • Notify for an operation (excludes applying pesticides by helicopter) (ORS 527.670)
  • Notify the Departments of Forestry and Revenue of my intent to harvest timber (ORS 321.550)
  • Before you use fire, contact the local office of the Oregon Department of Forestry or Forest Protective Association to see if additional burn permit and/or Smoke Management Program regulations apply.

Oregon Department of Forestry Contact Information

ODF OFFICE: DALLAS
ODF DISTRICT:
West Oregon
ADDRESS:
825 Oak Villa Rd
Dallas, Oregon, 97338
PHONE:
(503) 934-8146
ODF FORESTER
NAME:
Dave Thompson

Notifier

CLIFFORD BARNHART
COMPANY:
Stuntzner Engineering & Forestry
ADDRESS:
PO Box 167
Dallas, Oregon, 97338
PHONE:
(503) 623-9000
EMAIL:
Not Available

Notifier Comment

No Notifier comments have been made on this NOAP.

Landowner(s)

Landowner Responsibility
CLIFF BARNHART
COMPANY:
Barnhart Family Limited Partnership
ADDRESS:
14165 Wildwood Road
Philomath, Oregon, 97370
PHONE:
(503) 623-9000
Landowner Responsibility

The Landowner is responsible for reforestation. Early consultation with the ODF Forester is advised.

On-site inspections may be conducted by Oregon Department of Forestry employees to ensure compliance with all laws and rules governing fire protection and forest practices on private land.

For activities or operations changing the land to a non-forest use, the applicant is advised to contact the appropriate local government regarding land use regulations which may apply to the future use or development of this site.)

Timber Owner

Timber Owner Responsibility
CLIFF BARNHART
COMPANY:
Barnhart Family Limited Partnership
ADDRESS:
14165 Wildwood Road
Philomath, Oregon, 97370
PHONE:
(503) 623-9000
Timber Owner Responsibility

If timber harvesting is part of the proposed operation, the party shown below, owning the timber at the point it is first measured, is responsible for payment of Oregon timber taxes.

Fire Emergency Contact

NAME:
Cliff Barnhart
PHONE:
(503) 260-5630

Units / Activities / Operators

6.8 ACRES
  • Clearcut/Overstory Removal

    METHOD(S):
    Ground
    OPERATOR:
    Bill Wischnofski
    COMPANY:
    Elkhorn Timber
  • Treatment of Slash

    METHOD(S):
    Burning - piles
    OPERATOR:
    Nick Domes
    COMPANY:
    Nick's Timber Services Inc

This Unit falls within the following Regulated Use Areas: WO-3

A Statutory Written Plan is required for the resources detected in or near this Unit if activities occur within:

100 Feet of
  • Unknown: - Type F Stream
300 Feet of
  • None detected.
2.6 ACRES
  • Clearcut/Overstory Removal

    METHOD(S):
    Ground
    OPERATOR:
    Bill Wischnofski
    COMPANY:
    Elkhorn Timber
  • Treatment of Slash

    METHOD(S):
    Burning - piles
    OPERATOR:
    Nick Domes
    COMPANY:
    Nick's Timber Services Inc

This Unit falls within the following Regulated Use Areas: WO-3

A Statutory Written Plan is required for the resources detected in or near this Unit if activities occur within:

100 Feet of
  • Unknown: - Type F Stream
300 Feet of
  • None detected.
6.4 ACRES
  • Clearcut/Overstory Removal

    METHOD(S):
    Ground
    OPERATOR:
    Bill Wischnofski
    COMPANY:
    Elkhorn Timber
  • Treatment of Slash

    METHOD(S):
    Burning - piles
    OPERATOR:
    Nick Domes
    COMPANY:
    Nick's Timber Services Inc

This Unit falls within the following Regulated Use Areas: WO-3

Site Conditions

RESOURCES THAT MAY REQUIRE A WRITTEN PLAN
  • Stream within 100 feet of area.

Uploaded Documents

You must be signed in as a registered user with FERNS to see documents associated with this NOAP.

Formal Comments

COMMENTS
  • Dave Thompson
    4/6/2022 4:18:46 PM
    Uploaded an amendment to the SWP.
  • Dave Thompson
    3/24/2022 4:55:31 PM
    After reviewing your Statutory Written Plan, I offer you the following comments: Fully implementing this written plan is likely to achieve the resource protection standards. This operation will be evaluated on the basis of how well required practices are applied and how well required resource protection is achieved.
  • Dave Thompson
    3/9/2022 3:26:12 PM
    A Statutory Written Plan is required, and has been submitted with this NOAP, for any operational activity that will directly affect the RMA of the Type F stream. Stewardship Forester comments may be provided following the 14-day open comment period.