- OPERATION NAME: C1675 Rd 3252
- SUBMIT DATE: 05-17-2021
- NOAP ID: 2021-740-06227 (c)
- LANDOWNER STATUS: The Landowner is not a Small Forestland Owner.
- Apply for a permit to use fire or power-driven machinery (PDM) (ORS 477.625)
- Notify for an operation (excludes applying pesticides by helicopter) (ORS 527.670)
- Notify the Departments of Forestry and Revenue of my intent to harvest timber (ORS 321.550)
NOAP CONTINUATIONS
-
Issued on: 12-16-2021Expires on: 12-31-2022Continuation issued by Alicia Nukusuk
Oregon Department of Forestry Contact Information
ODF OFFICE: COOS BAY
Coos Bay, Oregon, 97420
ODF FORESTER
Notifier
WEYERHAEUSER COOS BAY
- COMPANY:
- Weyerhaeuser
- ADDRESS:
- 63459 Olive Barber Road
Coos Bay, Oregon, 97420 - PHONE:
- (541) 267-1850
- EMAIL:
- Not Available
Landowner(s)
WY COOS BAY
- COMPANY:
- Weyerhaeuser Company
- ADDRESS:
- 63459 Olive Barber Rd
Coos Bay, Oregon, 97420 - PHONE:
- (541) 269-5540
The Landowner is responsible for reforestation. Early consultation with the ODF Forester is advised.
On-site inspections may be conducted by Oregon Department of Forestry employees to ensure compliance with all laws and rules governing fire protection and forest practices on private land.
For activities or operations changing the land to a non-forest use, the applicant is advised to contact the appropriate local government regarding land use regulations which may apply to the future use or development of this site.)
Timber Owner
WYNR COOS BAY
- COMPANY:
- Weyerhaeuser NR
- ADDRESS:
- 63459 Olive Barber Rd
Coos Bay, Oregon, 97420 - PHONE:
- (541) 269-5540
If timber harvesting is part of the proposed operation, the party shown below, owning the timber at the point it is first measured, is responsible for payment of Oregon timber taxes.
Fire Emergency Contact
- NAME:
- Bobby Watkins
- PHONE:
- (541) 267-1868
Legal Notice
WRITTEN PLANS
A Written Plan (in addition to this NOAP) is required before operation activities can begin near the protected resources listed with the Unit information or Site Conditions below or otherwise described to you by the ODF Forester (OAR 629-605-0170(2), (3), and (5)). The Written Plan must describe in detail how the resource(s) will be protected during the operation. There is a waiting period for Written Plans that is separate from the notification waiting period. Contact your ODF Forester for more information.
Units / Activities / Operators
-
Clearcut/Overstory Removal
- METHOD(S):
- Cable, Ground
- OPERATOR:
- WY Coos Bay
- COMPANY:
- Weyerhaeuser Company
-
Felling Harvest Unit (No yarding/decking)
- METHOD(S):
- Manual, Mechanical
- OPERATOR:
- LBA Contract Cutting
- COMPANY:
- LBA
This Unit falls within the following Regulated Use Areas: CS-2
A Statutory Written Plan is required for the resources detected in or near this Unit if activities occur within:
- Unknown: - Type F Stream
- Wetlands: Freshwater Pond
- None detected.
Site Conditions
- Stream within 100 feet of area.
- Slope of steepest 1/3 area: 70 %.
Uploaded Documents
You must be signed in as a registered user with FERNS to see documents associated with this NOAP.
Formal Comments
-
Jennifer Ward
6/7/2021 9:34:31 AM
Written plan has been reviewed. Fully implementing this written plan is likely to achieve compliance with resource protection standards in the forest practice rules/law that it addresses. This operation will be evaluated on the basis of how well required practices are applied and how well required resource protection is achieved.
-
Jennifer Ward
5/25/2021 1:56:47 PM
Please be aware there may be a wetland/pond that is less than an acre but greater than a quarter of an acre located on the southern unit boundary where it intersects with Lake Creek-T. Protection measures require leaving snags and down wood and protecting soil from disturbance in wetland areas greater than 1/4 acre but less than than 8 acres. See OAR 629-655-0000 for details.
-
Jennifer Ward
5/25/2021 1:55:08 PM
Required Statutory Written Plan was received on 5/17/2021; comment period is in effect.
Notifier Comment